Simon Paul Salon
Client:
Simon Paul Hair & Beauty, Solihull
Project:
Fitting out of large hair and beauty salon
Contract Duration:
7 weeks
Description of works:
 
Combine two existing units into a new, single-use salon. The seven weeks programme was carried out in two phases. Works involved erecting new stud walls, forming the new layout, fitting new plasterboard ceilings, joinery work, laying new ceramic floor tiles and full redecoration. All electrics were re-wired and a new air conditioning system installed.